Very nice quick local job to our shop. ONLY took two days from start to finish!! You GO guys!!!!
First Bus Company
Springfield, MA
12,000 SQFT Replacement
Roof Details –
Slice existing TPO roof membrane into 5’ by 5’ grid pattern. Install (1) layer of 1” insulation. New Carlisle Rhinobond .060 TPO membrane. Custom Es-1 snap metal. Job duration (2) days.